# Tasks and the timeline (BreeStudio documentation)

Plan a project’s work in phases, set what each task waits on, and keep dates honest on the timeline.

Source: https://breestudio.com/docs/tasks · Updated 2026-11-12 · Describes the BreeStudio web app at https://app.breestudio.com. Words in **bold** are the app's own button, tab and menu names.

## Two views of the same tasks

The **Tasks** tab has two views. **Main table** lists the tasks in groups, one per phase, each with its colour. **Timeline** draws the same tasks as bars across weeks or months. A change in one shows in the other.

A new project starts with an empty table. **Start from a template** fills it with your phases and tasks, dated from the start date. See [Templates](https://breestudio.com/docs/templates).

## Columns and values

The table shows Task, Description, Status, Person and Date. Add Priority, Due date, Approval, Time tracking, Files, Tags or Waits on from the add-column menu.

| Column | Values |
| --- | --- |
| Status | To Do, Working on it, Stuck, In Review, Done |
| Priority | Urgent, High, Medium, Low |
| Approval | Pending, Approved, Rejected, Needs Changes |

**Pin name** keeps the task’s name in view while you scroll sideways.

## Subtasks and what a task waits on

Break a task into subtasks; BreeStudio tells you when the last one is done. To show what has to finish first, set what a task **Waits on**, or use **Make it wait on a task** in its side panel. Two tasks can’t wait on each other. Completing a task while a task it waits on is still open asks you first.

## Send work for review

Move a task to **In Review** when it needs a second look. When someone has to sign it off, add the Approval column: Pending, Approved, Rejected or Needs Changes. Steps shared with the client reach their Approvals page. See [Clients, guests and approvals](https://breestudio.com/docs/clients).

## Plan on the timeline

- Drag a bar to move it, and pull its end to change its length. Bars snap to whole days.
- Draw a line from one bar to another to make the second task wait on the first.
- Switch between **Day**, **Week** and **Month**, and press **Today** to come back to now.

Dates never move on their own. When a task starts before a task it waits on finishes, BreeStudio says so and offers **Reschedule**, for that task or for all of them at once.

## Key dates

On the timeline, **Key date** adds a named date, such as Design sign-off, to the **Key dates** lane. Drag its diamond to move it, rename or delete it, and use **Mark as reached** when it happens. A key date past its day shows red until it is reached.

When a fee payment is billed on a key date, marking it reached makes the payment ready to invoice, and the toast opens the payments. See [Finance](https://breestudio.com/docs/finance#payment-schedules).

## Change many tasks at once

Select tasks in the table and a bar appears: set the status, **Assign to**, set the priority or the due date, or delete. Under **More** you can set new dates or shift them by a number of days, earlier or later, make them wait on a task (**Wait on a task…**), **Stop waiting**, or move them to another group.

## Inside a task

Open a task to see its side panel. **Updates** holds the comments, with replies and likes. **Files** holds what is attached to the task, saved with the project’s files. **Activity** lists every change. The due date has quick picks: Today, Tomorrow and Next week.

## Filter and export

**Filter** shows all tasks, only late ones, those with no due date or those that are stuck, for everyone or one person. The **⋯** menu holds **Apply a template**, **Save as template** and **Export as CSV**, which exports what is shown, filtered or not.

The CSV has these columns: Task, Phase, Status, Priority, Assigned to, Start, Due, Key date, Subtasks done, Description and Created.